City of Salina approves 2026 Capital Improvement Plan

Posted Nov 25, 2025 10:35 AM

By: NICOLAS FIERRO

Salina Post

The City of Salina presented on Monday's City Commission meeting, the plan of the 2026-2030 Capital Improvement Plan (CIP).

The CIP is divided into two categories: 

- 5 year CIP (typically large dollar projects with long life cycles that may be funded with current cash, but are often funded with debt financing).

- 2026 Sub-CIP (mechanism to provide pre-approval by the City Commission for larger cash supported items broken out into six categories: CIP Planning, Building & Facilities, Parks, Streets,Vehicles & Equipment and Water/Wastewater Enhancements).

The 2026-2030 provides an anticipated schedule of capital projects and capital outlay for the next 5 years, along with anticipated funding sources.

2026 Cash proposed projects

- Downtown wayfinding signs.

- Brookwood Trail Pedestrian Bridge.

- 9th & Ohio updated traffic signal interconnect system.

- Design and construction of culvert at Northwood and Fairdale.

- Comprehensive planning and zoning code updates.

Total: $1,210,000

2026 Debt finance proposed projects

- Design of Ohio and Schilling roundabout.

- E. Magnolia bridge and road improvements.

- N. Ohio overpass painting.

- Bifra runway repairs and construction of new landfill scales.

- Airport water mains

Total: $9,400,000

2026 Sub-CIP

- $743,500 = Repairs in maintenance to buildings and facilities.

- $790,000 = Parks and maintenance.

- $5,787,000 = Street maintenance.

- $2,000,000 = System enhancements (for utility systems).

- $4,813,211 = Vehicle and equipment, purchase/replacements.

- $203,383 = Kenwood Cove maintenance. 

Projects for 2027-2030 will be re-evaluated each year and adjusted.