SALINA, KAN. - More construction to be aware of starting Wednesday.

Beginning Wednesday, November 18, 2026, at 6 a.m., Ohio Street will be reduced to one Northbound Lane in the 600 block between Greeley Avenue and Edison Place.
At the same time Edison Street will be closed west of Ohio Street to Westchester Drive.
These temporary lane closures will allow McCownGordon Construction to complete water utility Tie-ins at the Salina Health Education Foundation.
Work is expected to take approximately 2 weeks and is scheduled to be completed by Wednesday, December 2, 2026, weather permitting.
Motorists are encouraged to use caution when traveling through the area, follow posted traffic control signs, and allow extra time for possible delays.