City of Salina annual chip seal project schedule

Posted Aug 29, 2023 1:38 PM

City of Salina

On Tuesday through Thursday, Aug. 29- through Sept. 1, APAC-Kansas, Inc., Shears Division of Emporia, Kansas will perform the City of Salina’s annual chip seal project. The schedule is as follows, weather permitting:

Microsurfacing schedule <b>Image Courtesy City of Salina</b>
Microsurfacing schedule Image Courtesy City of Salina

Chip sealing is a method of pavement surface treatment which prolongs the serviceability of streets by sealing the surface. Combined with joint and crack sealing, this surface treatment program extends the service life of pavement.

Owners and occupants along residential streets will be notified ahead of time that their streets will be closed to traffic while the work is being completed. Motorists are encouraged to avoid the construction altogether and find alternate routes to their destinations while the work is occurring.

The $280,000 project is a major component of the City of Salina's 2023 $4.7 million maintenance capital improvement program.