The approval of the 2026-2030 City of Salina Capital Improvement Program (CIP) included several road design, construction, painting and improvements.
Those project included:
Ohio/Schilling Roundabout
Design and construction to improve the functionality and safety for all users of the intersection in support of continued expansion of the area along S. Ohio Street and Schilling Road.
Project Cost: $2,300,000
East Magnolia Road and Bridge
Improvements to replace the existing bridge with a wider, that will accommodate the hike and bike trail connection from the Soccer fields to Markley Road.
Project Cost: $7,600,000
North Ohio Overpass Painting
Due to rusting.
Project Cost: $1,000,000
Berkley Family Recreation Area Runway Repairs
Project Cost: $300,000